Optimasi Pelaksanaan Proyek Jalan Dengan Earned Value Dan Fast Track

https://doi.org/10.35583/js.v10i1.13

Authors

  • Desi Yasri Sekolah Tinggi Teknologi Pekanbaru
  • Andi Yuliardi Sekolah Tinggi Teknologi Pekanbaru
  • Randhi Saily Sekolah Tinggi Teknologi Pekanbaru

Keywords:

Delay, Fast Track, Earned Value Analysis

Abstract

Sei Akar – Bagan Jaya Mayor Rehabilitation Project is located on the Sei Akar – Bagan Jaya road, Indragiri Hilir Regency, Riau Province. Corresponding on the project progress report status up to week 18 or 119 calendar working days, the project has been behind schedules 0.871 % and can lead to project failure. Collaboration of Earned Value Analysis, in time and cost monitoring project performance and Fast-Tracking, in accelerating, overlapping or compressing projects, schedule can be optimized project schedule and prevented from contractual penalties. Earned value analysis forcast additional time for 13 days and cost of Rp. 83.390.308,59 for direct cost, Rp.68.793.391,35 for indirect cost, and Rp.181.614.553,16 for penalties. Implementation of Fast Track in anticipating delays for 13 days, the possibility enclose to Tack Coat activity (42 days) and Asphalt Concrete-Binder Course Work activity (35 days). Both activities have met the rules in the application of fast tracking and have the longest duration. Therefor, has the greatest potential reduction in time.

Downloads

Download data is not yet available.

Published

2022-06-30

How to Cite

Yasri, D., Yuliardi, A., & Saily, R. (2022). Optimasi Pelaksanaan Proyek Jalan Dengan Earned Value Dan Fast Track. SAINSTEK, 10(1), 89–95. https://doi.org/10.35583/js.v10i1.13

Issue

Section

Articles